Progress meetings reports

    TOC 

    Other pages:

     

    1st Progress Meeting report (13th December 2011):

    • Board test plan in development (see respective section for details);
    • Board production plan in development (see respective section for details);
    • Board enginnering design in development (see respective section for details);
    • Firmware validated for path one and two;
    • PCI express generation 2 validated;
    • RTM modifications in standby until all analog IO channels are tested;
    • Board tests to be done listed into the To test section;
    • Searching in progress for a new PCB design company to make changes in order to improve the ATCA-IO-PROCESSOR prototype PCB;

     

    2nd Progress Meeting report (10th January 2012):

    Hardware:

    • Board test plan first draft ready;
    • Board production plan first draft ready;
    • Board enginnering design first draft ready;
    • Hardware engineering files and hardware production files to be stored on ITER SVN, folder structure created.

    Firmware:
         - Improving the stability on the continuos aquisition data  streaming ( DMA channel #2)

    Software:

    • Luca Boncagni finished his develloping and tunning the MARTe system to receive RT data
      (report still to be finished)
    • Progressing on device driver devellopemt to handle DMA channel #2

     

    Next month

    Hardware:

    • Board production (4 units) in progress;
    • Hardware engineering files and hardware production files to be stored on ITER SVN, files upload in progress;
    • RTM modifications in progress;
    • Board tests to be done listed into the To test section;
    • Searching in progress for a new PCB design company to make changes in order to improve the ATCA-IO-PROCESSOR prototype PCB.

    Firmware:
        - Integration of IPMC module with geographical address of ATCA boards on system
        - Implementattion of fast data dat transfer ( DMA channel #3)
    Software:
     
       -Progressing on device driver devellopemt to handle DMA channel #2 and #3
        -device Suport modules to  EPICS

     

    3rd Progress Meeting report (9th February 2012):

    Hardware:

    • Majority of hardware engineering files and hardware production files uploaded to SVN;
    • Board production in progress, but with 3 weeks delay due to components lead time changes;
    • RTM modifications done, board assembled and ready to be tested;
    • AXIe synchronization signals fully tested.

    Firmware:

    Software:

     

    Next month

    Hardware:

    • Test details to be added to the test plan document;
    • Board production in progress;
    • FPGA and IPMC hardware engineering files and hardware production files to be stored on ITER SVN;
    • Board tests to be done listed into the To test section;
    • Searching in progress for a new PCB design company to make changes in order to improve the ATCA-IO-PROCESSOR prototype PCB.

    Firmware:
    Software:

     

    4th Progress Meeting report (7th March 2012):

    Hardware:

    • All hardware engineering and production files uploaded to SVN, except IPMC software and FPGA firmware (binary and source files);
    • Board production in progress, but with 6 weeks delay due to recent IST administrative problems;
    • RTM modifications done, board assembled and ready to be tested;
    • More tests and test details added to the test plan document;

     

    Firmware:

    Software:

     

    Next month

    Hardware:

    • Board production in progress;
    • FPGA and IPMC hardware engineering files and hardware production files to be stored on ITER SVN;
    • Board tests to be done listed into the To test section;
    • Searching in progress for a new PCB design company to make changes in order to improve the ATCA-IO-PROCESSOR prototype PCB.

    Firmware:
    Software:

     

    5th Progress Meeting report (13th April 2012):

    Hardware:

    • 3 Boards produced and tests for validation started.

     

    Firmware:

    • Final version ready.

     

    Software:

     

    Next month

    Hardware:

    • FPGA and IPMC hardware engineering files and hardware production files to be stored on ITER SVN (binary and source files);
    • Boards validation;
    • Searching in progress for a new PCB design company to make changes in order to improve the ATCA-IO-PROCESSOR prototype PCB.

     

    Firmware:

    • Final version validation;


    Software:

     

    6th Progress Meeting report (11th May 2012):

    Hardware:

    • ~30% of ADC modules failed (soldering problems).

     

    Firmware:

    • Final version validation in progress.

     

    Software:

     

    Next month

    Hardware:

    • Failed ADC modules validation;
    • 2 Boards to be sent ASAP;
    • FPGA and IPMC hardware engineering files and hardware production files to be stored on ITER SVN (binary and source files);
    • Searching in progress for a new PCB design company to make changes in order to improve the ATCA-IO-PROCESSOR prototype PCB.

     

    Firmware:

    • Final version validation;


    Software:

     

     

    7th Progress Meeting report (22nd June 2012):

    Hardware:

    • One full populated (40 ADC's and 8 DAC's) ATCA-IO-PROCESSOR module sent (June 21);
    • Patch panel and test cables sent (June 21);
    • One PCIe host interface card and a 3 meters PCIe cable sent  (June 21).

     

    Firmware:

    • Final version with RT e CA fully validated.

     

    Software:

    •     RPM available with Linux device driver, command line applications and a CSS/EPICS GUI hardware test program.

     

    Next month

    Hardware:

    • Second ATCA-IO-PROCESSOR board to be sent;
    • Test Plan adjustments if needed;
    • FPGA and IPMC hardware engineering files and hardware production files to be stored on ITER SVN (binary and source files);
    • Searching in progress for a new PCB design company to make changes in order to improve the ATCA-IO-PROCESSOR prototype PCB.

     

    Firmware:

    • Final version DDR3 validation;


    Software: