    First Progress Meeting report:

    • Board test plan in development (see respective section for details);
    • Board production plan in development (see respective section for details);
    • Board enginnering design in development (see respective section for details);
    • Firmware validated for path one and two;
    • PCI express generation 2 validated;
    • RTM modifications in standby until all analog IO channels are tested;
    • Board tests to be done listed into the To test section;
    • Searching in progress for a new PCB design company to make changes in order to improve the ATCA-IO-PROCESSOR prototype PCB;

     

    Second Progress Meeting report:

    • Board test plan first draft ready (hardware);
    • Board production plan first draft ready (hardware);
    • Board enginnering design first draft ready (hardware);
    • Boards production in progress (quantity 4);
    • Hardware engineering files and hardware production files to be stored on ITER SVN, folder structure created and files upload in progress; 
    • RTM modifications in progress;
    • Board tests to be done listed into the To test section;
    • Searching in progress for a new PCB design company to make changes in order to improve the ATCA-IO-PROCESSOR prototype PCB;