No headers2012-01-12
- (Update) Boards production: quotation for fabrication received. New comparison study between the quotations received until now is here.
- Development of firmware program for additional hardware programming
- Found cause of Front Board malfunction - incorrectly soldered component. This error was found on yet another module that was reportedly malfunctional and was only used to test carrier mechanics. Solder rework required at IPFN.
2012-01-16
- Component stock verification for ATCA-PTSW-AMC4.
2012-01-17
- Component stock verification for ATCA-PTSW-AMC4_RTM.
- PCB gerber files sent for manufacturing.
2012-01-18
- Ordering components for ATCA-PTSW-AMC4 modules.
- Creating file structure at ITER SVN
2012-01-19
- Ordering components for ATCA-PTSW-AMC4 modules.
- Add/update files to structure at ITER SVN
- Gerber modifications required by Lusodabel to manufacture RTM PCBs
2012-01-20
- Add/update files to structure at ITER SVN
- Test firmware for ATCA-PTSW-AMC4
2012-01-23
- Bill of Materials of ATCA-PTSW-AMC4 for HFA
2012-01-24
- Bill of Materials of ATCA-PTSW-AMC4_RTM for HFA
2012-01-25
- Received carrier module after rework at IPFN
- Test supply voltages and programmimg FPGA OK
- PCIe refclk is now available at the FPGA
- Unable to establish PCIe communication with 3 and 7m cable
2012-01-26
- Continuing tests using other motherboards.
- Impedance measure of PCIe lanes and Refclk.
- Board cleaning.
- Lusodabel reports 2 ATCA-PTSW-AMC4 modules didn't pass electrical tests and will be sent later.
2012-01-27
- Arrived 5 ATCA-PTSW-AMC4 and ATCA-PTSW-AMC4_RTM pcbs.
- finalizing production package for ATCA-PTSW-AMC4_RTM.
- contuning test of current hardware versions using different re-driver configurations.
2012-01-30
- PCIe communication was achieved and module is detected via lspci command. Tests will continue upon arrival of newer version of the ATCA-PTSW-AMC4_RTM.
- Sending ATCA-PTSW-AMC4_RTM pcbs to HFA.
2012-01-31
- Reviewing missing parts of BOMs, pending orders/acquisitions.
2012-02-01
2012-02-02
2012-02-03
- Answering to reviews of the ITER documents.
- correction of some wording issues regarding ITER documentation.
2012-02-06
- new quotation request HFA (ATCA-PTSW-AMC4_RTM).
- started ellaborating new versions for ITER documents.
2012-02-07
- discussing - device driver, firmware, test plan modifications.
- writing progress report.
- preparing new front panel files for manufacturing.