No headersSecond Progress Meeting report:
- ATCA-PTSW-AMC4 and ATCA-PTSW-AMC4_RTM modifications required for production ready (as of late Nov. 2011).
- ATCA-PTSW-AMC4 user manual first draft ready
- Board production plan first draft ready;
- Board enginnering design first draft ready;
- Boards production: quotations for fabrication received - evaluation in progress (see attached files). A comparison study between the quotations received is written here.
- ATCA-PTSW-AMC4 and ATCA-PTSW-AMC4_RTM "bill of materials" concluded.
- Component stock verification - in progress (about 80% of components arrived)
- Hardware engineering files and hardware production files to be stored on ITER SVN - awaiting access login.
- Board tests to be done listed into the Test Plan section - in progress;
- AMC site and PCIe test are being made with the current hardware versions;
-