    Second Progress Meeting report:

    • ATCA-PTSW-AMC4 and ATCA-RTM-Host modifications ready (as of late Nov. 2011).
    • ATCA-PTSW-AMC4 manual first draft ready
    • Board production plan first draft ready;
    • Board enginnering design first draft ready;
    • Boards production:  quotations for fabrication received - evaluation in progress (see attached files). A comparison study between the quotations received is written here.
    • ATCA-PTSW-AMC4 and ATCA-RTM-Host BOMs concluded.
    • Component stock verification - in progress (about 80% of components arrived)
    • Hardware engineering files and hardware production files to be stored on ITER SVN - awaiting access login. 
    • Board tests to be done listed into the Test Plan section - in progress;
    • Further tests are being made with the current hardware versions;